North Loop Reconstruction & Pedestrian Improvements Update 9/19/19

NORTH LOOP PAVING PROJECT

WORK THIS PAST WEEK

5th Ave N 

  • Continued with driveway placement

  • Continued with side sidewalk placement

  • Placed decorative rail and black concrete between Washington and 3rd St N

7th Ave N

  • Continue work on the north side of Washington

  • Placed decorative rail and black concrete between Washington and 3rd St N

8th Ave N 

  • Continued placing sidewalks

  • Continued placing driveways

  • Installed concrete parking bays

  • Placed decorative rail and black concrete between Washington and 3rd St N

  • Continue work on the north side of Washington

9th Ave N 

  • Continued placing driveways

  • Continued placing sidewalks

  • Placed decorative rail and black concrete between Washington and 3rd St N

  • Continue work on the north side of Washington

3rd St N

  • Completed underground utility work

  • Installed most of the curb and gutter

  • Continued with power pole relocation

  • Installed foundations for new lights

WORK ANTICIPATED FOR THE REMAINDER OF THIS WEEK AND NEXT WEEK

5th Ave N 

  • Finish driveway placement

  • Finish curb and gutter placement

  • Continue with sidewalk placement

  • Possibly place third lift of asphalt at the end of next week (9-26 to 9-27)

7th Ave N

  • Continue work on the north side of Washington

  • Finish placing driveways

8th Ave N 

  • Finish placing sidewalks

  • Finish placing driveways

  • Finish placing parking bays

  • Install decorative rail between Washington Ave and 3rd St N

  • Continue work on the north side of Washington

  • Possibly place a first and second lifts of asphalt at the end of next week (9-26 to 9-27)

9th Ave N 

  • Continue placing driveways

  • Continue placing sidewalks

  • Finish placing parking bay

  • Continue work on the north side of Washington

  • Possibly place the remaining first lift and second lift of asphalt at the end of next week (9-26 to 9-27)

3rd St N

  • Complete underground utility work

  • Finish utility pole relocates

  • Finish installation of curb and gutter

  • Start sidewalk installation on north side

  • Grade for sidewalk on south side

  • Start driveway installation

  • Begin installation of parking bays

  • Possibly place a first and second lifts of asphalt at 10th Ave N and 3rd St N (9-26 to 9-27)

NORTH LOOP PEDESTRIAN IMPROVEMENT PROJECT

Sewer crews are retuning early next week and the concrete crew will be following behind them.  Due to the multiple construction projects (developments and water work) some of the intersections will have to be completed either later in the season or early next year.

WORK THIS PAST WEEK

  • Storm sewer work at 2nd St N and 5th Ave N

  • Storm sewer work at 2nd St N and 3rd Ave N 

WORK FOR THE REMAINDER OF THIS WEEK AND INTO NEXT WEEK

The concrete crews will be following the sewer crews work over the next week includes:

1ST St N

  • 4th Ave SE and NW corner

2nd St N 

  • 1st Ave N – Currently there are issues getting into any of these corners, do to existing construction.

  • 3rd Ave N – SW corner – NOTE: This corner contains more work and may be under construction for a few more weeks

  • 5th Ave N – SE cornerAs always, feel free to contact Project Manager Stephanie Malmberg at (612-673-3365) or John Benjamin (651-443-1096) with any construction related questions or concerns.

Contact Information

Project Manager:

Stephanie Malmberg, stephanie.malmberg@minneapolismn.gov, 612-673-3365

Chief Field Inspector:

John Benjamin, john.benjamin@minneapolismn.gov, 651-443-1096 

N. Loop  2 Neighborhood Preconstruction Meeting Invite.docx.jpg